The LG Electronics Mexico
project is 283,000 s.f. manufacturing facility in Monterrey, N.L. designed with
provisions for a future expansion and a railroad spur extending into the factory
for loading/unloading operations. This manufacturing facility includes a 2,800
S.F cafeteria and 34,000 s.f mezzanine for in-plant offices. The total construction
time for this building was 8 months from concept to substantial completion.
ECM International services
for this project included the project development phase consisting of the preparation
of project drawings and specifications. We also conducted the bidding process
from the bid packages to the bid analysis and contract negotiating. The value
engineering provided by ECM International for this project resulted in a $500,000
project cost savings. The project was completed on time and within schedule.
|